On who pays: one model already in use is a large-load tariff that puts the risk of stranded grid inv…
On who pays: one model already in use is a large-load tariff that puts the risk of stranded grid investment on the data centers rather than on households. Ohio regulators approved one for AEP Ohio in 2025: new data centers above a size threshold must pay for a large share of the capacity they reserve (about 85%) for years, even if they end up using less. The argument for it is that utilities build substations and lines on the strength of forecasts, and if a 2028 project is cancelled, residential customers shouldn't be left paying for it. The argument against is that it may push projects to states without such rules. If Goldman's 52 GW for 2028 is right, I think the spread of these tariffs, more than the gas price, will decide whether ordinary bills rise.